NCEP Modeling Synergy Meeting
Highlights: August 14, 2006
This meeting was led by Peter Manousos
and attended by Mark Iredell, Geoff Dimego, Brent Gordon, Jim Hoke, Dave Plummer, Bill Bua,
Mary Hart, Ed Danaher, Joe Sienkiewicz, and
1. CCS
Brent
Gordon reported the moratorium will commence on August 23rd. The new system is being tested by IBM and
will be handed over to NCO that same week
2. NOTES
FROM EMC
2a. Global Modeling Branch:
Mark Iredell reported that the code for a
minor implementation parallel will implemented pending NCEP OD approval Aug
22. Changes to GFS will include changes
to ozone physics, glacial ice physics, and Antarctic land/ice changes. The change will NOT include a transition to a
new coordinate system.
2b.
Mesoscale Modeling Branch (MMB):
Geoff Dimego reported a crisis change will be implemented to the
2c. Global Ensemble Prediction System:
Nothing new reported due to the impending
moratorium. An OSIP team was formed to look into issues of ensemble
distribution to AWIPS, which presently gets global ensemble data only to 84
hours, only from 10 of the now-14 members and no statistical data (mean/spread,
probability), and does not get any of the new bias-corrected output. It may
take several years for any changes to eventually reach deployment in a future
AWIPS build.
2d.
Nothing new reported due to the impending
moratorium.
2e. Marine Modeling and Analysis Branch
(MMAB):
Regina Nichols stated the Great Lakes WaveWatch3 model will be implemented Aug 22. However, it will not be getting into AWIPS until OB9 (tentatively late 2008).
3. The next meeting will
be held Monday October 30 at noon in EMC Rm 209 with remote
conference capability.