NCEP Synergy Meeting Highlights: March
30, 2009
This meeting was led by Bill Bua and
attended by John Ward; Geoff DiMego; Stephen Jascourt; Mike Brennan and Richard
Pasch, NHC; Dave Novak and Keith Brill, HPC; Steve Weiss and David Bright, SPC;
Bernard Meisner, Southern Region; David Myrick, Western Region; Bill Ward,
Pacific Region; and Vera Gerald, MMAB.
1. NCO
Geoff
DiMego reported on behalf of NCO. 95% of production is running on the new
Power-6 cirrus machine in
A
minor change to the RUC was being implemented on Tuesday, 31 March, including a
fix to bring in observations (daily NESDIS analysis) to correct snow cover errors in
the self-cycling, correct an error in calculation of forecast total
precipitation, and a change moving cloud analysis to the end of the analysis
process to make the forecast of cloud more consistent from run to run.
John
Ward noted that the computer moratorium is scheduled, per the IBM contract, to
end no later than October of 2009, and most likely will end in July of 2009.
2. NOTES FROM EMC
2a.
Global Climate and Weather Modeling Branch (GCWMB)
John
Ward reported that upgrades are still waiting in the queue for more computer
resources. Post-processing changes to
the GDAS need to be made to match the GDAS to the GFS. An eye will need to be
kept on the vortex relocation for hurricanes prior to implementation. For the
GFS, new post-processed fields are also to be added along with some bug fixes,
to the next minor implementation.
The
next GFS implementation contains a few bug fixes. Currently, a “null” test to produce
identical results to operations cannot be run with the current parallel GFS. GCWMB
wants to be able to get identical results as a “sanity check” prior to running
parallel tests. The problem has been
isolated to the aerosol routine in the code, and the global branch continues to
work on the issue.
Hurricane
WRF (HWRF) is now running in parallel; it will not be implemented on the
Power-5 (mist), but will be on the Power-6 (cirrus) for the entire season.
Changes to the HWRF include the effect of sea spray and gravity wave drag on
the forecast, and a change in the initialization procedure. TPC and
Testing
is being done on a new semi-Lagrangian model which will be run at T878. The
goal is to implement this model sometime between November 2009 and February
2010. In the meantime, further changes to the GSI are scheduled for 1st
quarter of FY 2010.
Climate
Forecast System (CFS): reanalysis and
reforecasting has been continuing on Power-5 (mist). Runs will be suspended if there is a need to
run production on mist. Next major
implementation for the CFS isn’t scheduled until 1st quarter of
FY2011.
Note
was made that global data will be put into GRIB2 format in parallel in a few
months to save disk space. This however will not be implemented operationally
until FY 2010.
2b.
Mesoscale Modeling Branch (MMB)
Geoff
DiMego reported on a minor implementation for the RUC (see NCO section).
WRF-NMM has a parallel on the Power-6 cirrus computer that
have 3 bug fixes. So far the aggregate impact is nil, though specific forecasts
may show small differences. This will be
made operational once the computer moratorium is lifted. Additional work will
be done to work toward having the NMM Data Assimilation System (NDAS) use the
same data as the GDAS; this will initially involve instituting monitoring of
data NOT used in NDAS but used in GDAS.
The
Real-Time Mesoscale Analysis (RTMA)
needs more disk space before it can be increased in resolution from 5 km to 2.5
km. This problem will not be solved
when the Power-6 becomes operational.
4-km
NMM and NMMb runs
have been placed on the development computer by Matt Pyle. MMB expects to make these operational in the
hi-res window slots later this year.
Recasting
MMB models into the NEMS framework is coming in FY2010.
2c.
Global Ensemble Prediction System
Yuejian
Zhu is testing a parallel GEFS run which increases resolution by about 50%,
which would be implemented once the computer moratorium is over.
2d.
Gridpoint Statistical Interpolation (GSI) Data Assimilation System
See
above on GFS/GSI implementation.
2e.
See
last month’s report; SREF still running in parallel on Power-6 cirrus computer
and MMB is hoping that implementation can take place before the moratorium is
lifted. SPC,HPC, and AWC are strongly in favor of this effort.
2f.
Marine Modeling and Analysis Branch
No
report.
3. FEEDBACK FROM OPERATIONAL CENTERS/REGIONS
Migration of data from Power-5 to Power-6 has not
resulted in any problems thus far. SPC and HPC have been actively getting data
from the new machine through dbnet.
The NCEP office move to the new building will not
result in a CCS moratorium, though there may be a bit of disruption of staff at
the in-house operational centers. As of
last week, there was still no further action on completion of the new
building. At present, the delay is at
least 7 months from the original planned move dates for each in-house center.
No issues were brought up by the regions
participating in the call.
4. The next Synergy Meeting will be
held at 2:30 pm EDT on Monday, 27 April 2009 in room 209, with remote
teleconferencing capability.